Job costing for pool and spa contractors: how to know which jobs actually made money

Cover tile: which of your jobs actually made money

Most pool and spa builders know, roughly, whether the year was good. Far fewer can say which of the 40 jobs they finished actually made money, which ones lost it, and why. That gap is not a bookkeeping detail. It is the difference between pricing the next job from evidence and pricing it from a gut feeling that was formed on the jobs that went well.

This guide is how we set up job costing for contractors in QuickBooks Online, what to track, where the numbers usually go wrong, and what a job-cost report should tell you at the end of every month. It applies to pool and spa builders, remodelers, and most specialty trades that quote a price per project.

What job costing actually is

Job costing means every dollar of cost is tagged to the job it belongs to, so revenue and cost can be compared per project rather than per company. On a $95,000 pool build, that means the excavation subcontractor, the shell, the plaster crew, the pump and filter, the permit fee, the crew hours and the portion of the foreman’s time all sit against that one job. At the end you know the job’s gross margin, and you can compare it with the estimate you quoted from.

Company-level books cannot do this. A company P&L that shows 28% gross margin might be hiding six jobs at 40% and four jobs at 5%. Until you can see the four, you keep quoting them.

Set up the file before you set up the jobs

Job costing fails in QuickBooks Online far more often because of setup than because of effort. Three things need to be right first.

1. Use Projects, not Classes, for jobs

QuickBooks Online Plus and Advanced have a Projects feature. Each job becomes a project under the customer, and every transaction can be assigned to it. Classes are better kept for something else, usually division or crew (new builds vs. service, or crew A vs. crew B), so you can slice the same data two ways. Using classes for jobs breaks the moment you have more than a few dozen, and it does not give you the per-project profitability screen that Projects does.

2. A cost-of-sales chart of accounts that matches how you build

Your cost of goods sold section should mirror the way a job is actually built, because that is how you estimate it. For a pool builder that usually means separate accounts for excavation, shell and steel, plumbing, electrical, tile and coping, plaster and interior finish, equipment (pumps, filters, heaters), decking and hardscape, permits and engineering, subcontractor labor, direct labor, and job materials not elsewhere classified. If your estimate template has a line for it, your chart of accounts should too. That is what makes estimate-vs-actual possible.

3. Decide what is direct labor and what is overhead

Crew wages that can be assigned to a job are direct labor and belong in cost of sales, tagged to the project. The office, the owner’s salary, the truck insurance and the yard lease are overhead. The mistake is to leave all wages in one payroll expense line, which makes every job look more profitable than it is. Run payroll so hours are captured by job, and post the payroll journal with the labor split to projects.

What to tag to every job, every week

Job costing is a weekly habit, not a month-end project. These are the transactions that need a project tag when they are entered:

  • Subcontractor bills: excavation, gunite, plaster, electrical, fencing. Match the bill to the sub’s quote and to the job.
  • Material purchases on the company card: the receipt from the supply house is the source document; the job is written on the receipt or captured in the field app.
  • Direct labor: hours by job from the time-tracking app, posted with the payroll journal.
  • Equipment rentals and dump fees.
  • Permit and engineering fees, which are easy to forget because they arrive before the job starts.
  • Customer deposits and progress invoices, so revenue sits against the same job as the cost.

Anything that cannot be assigned to a job should be questioned. Sometimes it is genuinely overhead. Often it is a job cost that nobody wrote a job number on, and it is quietly making every job look better than it was.

A company P&L that shows 28% gross margin might be hiding six jobs at 40% and four jobs at 5%. Until you can see the four, you keep quoting them.

The three places contractors’ job costs go wrong

Deposits booked as revenue

A $30,000 deposit on a job that has not started is not income yet. Book it to customer deposits (a liability), then recognise revenue as progress invoices are issued. If deposits go straight to income, the month you sign three contracts looks wonderful and the month you build them looks like a disaster, and job margins are meaningless.

Retainage ignored

On commercial and some residential work, 5 to 10 percent of each progress bill is held back until completion. That money is earned but not yet billable. Track it in a retainage receivable account per job. Otherwise the job looks under-billed, cash forecasts are wrong, and it is easy to forget to collect it.

Sales and use tax on materials treated inconsistently

In most states a contractor is the consumer of the materials that go into real property and pays sales tax to the supplier, or use tax if the supplier did not charge it. Whether tax is included in the job’s material cost changes the margin by several points. Pick a rule that matches your state, apply it to every job, and make sure use tax on out-of-state purchases is actually being accrued and filed.

What the monthly job-cost report should show

At month-end, for every open and recently closed job, the report we produce shows:

  1. Contract value, including approved change orders.
  2. Estimated cost by category, from the quote.
  3. Actual cost to date by the same categories.
  4. Cost to complete, from the project manager’s estimate.
  5. Projected gross margin at completion, against the margin you quoted.
  6. Billed to date, retainage held, and over- or under-billing.

The single most useful line is the projected margin at completion against the quoted margin. A job that was quoted at 32% and is tracking at 21% with 40% of the work remaining is a problem you can still do something about. A job you only find out about at the year-end tax return is not.

Change orders: where margin leaks out

Almost every job we take over has unbilled change orders. The customer asked for a bigger spa, the crew did it, and nobody invoiced the difference. The fix is procedural, not accounting: no change order is built until it is written, priced, signed and entered as an addition to the contract value in the project. Your bookkeeper should be reconciling the contract value in QuickBooks to the signed change-order log every month.

If you run your jobs in JobTread

Most of the pool and spa builders we work with do not live in QuickBooks. They live in JobTread: the estimate is built there, the budget is set there, purchase orders and subcontractor bills are approved there, and the crew logs time there. QuickBooks Online is where the books and the tax return come from. Job costing only works when those two systems agree, and in our experience that is where most contractors lose the thread.

This is how we set it up. We do the initial JobTread configuration and the QuickBooks connection ourselves for new clients, so if yours is not connected yet, that is part of onboarding rather than something you need to figure out first.

JobTread is the source of truth for the job. QuickBooks is the source of truth for the money.

Decide this once and do not blur it. The budget, the cost codes, the estimate-versus-actual and the change orders belong in JobTread. The bank reconciliation, the balance sheet, sales tax and the P&L belong in QuickBooks. When someone codes a cost in QuickBooks that was never entered in JobTread, or approves a bill in JobTread that never reaches QuickBooks, the two reports drift apart and the owner stops trusting both.

Make the cost codes and the chart of accounts map one-to-one

Every JobTread cost code should point at exactly one cost-of-sales account in QuickBooks, and the groups should match the way you build: excavation, steel, shotcrete, plumbing, electrical, tile and coping, decking, equipment, plaster and start-up. If JobTread has forty cost codes and QuickBooks has six accounts, that is fine, as long as each code rolls up cleanly. What you cannot have is a cost code that sometimes lands in “Materials” and sometimes in “Subcontractors” depending on who entered it.

Let the sync do the data entry, then reconcile it weekly

JobTread connects to QuickBooks Online, so customers, invoices and approved bills flow across instead of being typed twice. Turn that on, then treat the sync like a bank feed: something you check, not something you trust blindly. Once a week we run the same three checks for every client on JobTread.

  • Every bill approved in JobTread this week exists in QuickBooks, against the same job, with the same amount.
  • Every card and bank transaction in QuickBooks that is a job cost has a matching purchase order or expense in JobTread. Fuel, dump fees and the Home Depot run at 6am are the usual gaps.
  • Payroll hours by job in JobTread agree to the labor journal we post from Paychex or Gusto, so labor lands on the right job in both systems.

Deposits, draws and retainage still follow the accounting rules

JobTread will happily show a customer deposit as money received on the job. QuickBooks needs it as a liability until the work is done, for the reasons covered above. The same goes for progress billing and retainage. We let JobTread track the schedule of values and what has been billed, and we make the accounting entries in QuickBooks so the balance sheet is right at month-end. The two views are different on purpose; the mistake is trying to force one to look like the other.

The month-end check: two reports, one number

At close, total job costs for the month in JobTread should equal cost of sales on the QuickBooks P&L, give or take timing differences we can name. If they do not, we find out why before the reports go out, not in March when the tax preparer asks. That single reconciliation is what turns JobTread from a project tool into a job-costing system you can price the next pool from.

A realistic timeline to get this working

For a builder doing 20 to 60 jobs a year, moving from company-level books to clean job costing usually takes one to two months: a week to rebuild the chart of accounts and set up open jobs as projects, two to four weeks of catching up the current year’s transactions with job tags, then one normal monthly close to confirm the reports make sense. After that it is a weekly coding habit plus a monthly review.

If you cannot name your three least profitable jobs of last year, you do not have job costing yet. You have a P&L.

When to get help

You can do this yourself if you or someone in the office has a few hours a week and the discipline to tag every transaction as it happens. Where it usually breaks down is the catch-up, the payroll labor allocation and the month-end estimate-vs-actual, which is exactly the part that makes the whole exercise worth doing. If you want a second opinion on your current setup, bring your QuickBooks file to a call and we will tell you what we would change first.